List of Projects
Construction Division  

Projects Name Projects Type Location Execution Period Project Description (overview)
MIRADORE HOTEL HOSPITALITY PROJECT KHALDEH 2008-2010 an existing old building, including 3 basements, Ground Floor and 5 typical floors, roof floor,terraces, chalets and out door poolsBuilt up Area:
Activities :
Concrete repair, Structural Strengthening andModification, Reinforced concrete works,
waterproofing works.
Scope of works includes testing & evaluation of existing structure, design drawings, shop drawings & execution of civil works.
AL MAWARID BANK OFFICE BUILDING HAMRA 2003-2004 Renovation of an existing building consisting of one basement, ground floor and one upper floorThe new building is strengthened to have one additional Mezanine floor at basement, one additional Mezanine floor at ground floor, plus two additional floors to be constructed later at 2nd and 3rd floor level.Built up Area: 3200M2
Activities :
Concrete repair, foundation & skeleton strengthening, Reinforced Concrete Repair and structural steelsupporting system. screeding, façade treatment, Shotcreting & waterproofing works.
MANDALOUN "FOCH 230/231" OFFICE BUILDING BEIRUT CENTRAL DISTRICT 1997-1999 7 floors old building, stone and fair faced concrete façade including onebasementBuilt up Area: 3500M2
Activities :
Restoration ofan old building , stone & fair faced concrete facades , including extension of the basement under lot 231 building , foundation & skeleton strengthening , concrete repair systems , demolition & reconstruction of the upper floor as an open space flat , koutran doors & windows , louvers & double glazing , internal finishes , “fer forgé” , floor screeds and protection systems.
Scope of works includes construction programming, coordination, technical management, geotechnical survey & preparation of design and shop drawings for the above mentioned works.
L'ARCADIO "MAARAD 168" OFFICE BUILDING BEIRUT CENTRAL DISTRICT 1997-1999 7 floors old building , stone facades , including a new basement under the existing building.Built up Area:3500M2
Activities :
Restoration of an old building , stone facades , including a new basement under the existing building , foundation and skeleton strengthening , concrete repair systems , demolition and reconstruction of the upper floor as an open space , including skylight ceiling , koutran doors and windows , louvers and double glazing , internal finishes , fer forgé , floor screeds and protection systems . Scope of work includes construction programming, coordination, technical management, geotechnical survey, and preparation of design & shop drawings for the above mentioned works.
MARFAA 1144 HOSPITALITY PROJECT BEIRUT CENTRAL DISTRICT 1999-2002 And old existing building to be renovated and restorated with the addition of two basements and replacement or strengthening and repair of other upper slabs and building envelop of the remaining 6 upper floors.Built up Area: 4600M2
Activities :
Restoration of an old building including new two basement floors under the existing building & modification of the existing skeleton to accommodate a hotel building including demolition & concrete repair system , external envelop and stone facades, fer forgé ,red ceder shop fronts, doors & windows . Scope of works includes testing & evaluation of existing structure, design drawings, shop drawings & execution of civil works.
BEIRUT RIYADH BANK PROJECT INTERIOR CONSTRUCTION BEIRUT CENTRAL DISTRICT 2001-2003 1st & 2nd basement floors offices, to be renovated to a new design.Built up Area: 750M2
Activities :
Renovation of a 1st & 2nd basement floors including masonry & concrete work , plastering,acoustical ceiling, tiling, wood & metal works, partitions , painting, lighting & electrical power , bargler alarm system, CCTV, Sanitary works, HVAC ,DATA Network, Sound & Music network , etc...
Works include preparation of shop drawings & as built drawings.
BLOM BANK INTERIOR CONSTRUCTION (BORJ HAMOUD, SIYAH , TYR , BARBIR , BLISS ) 1991-1994 Renovation of bank branches' to ultra luxirious officesBuilt up Area: 7000M2
Activities :
Modification & rehabilitation including civil works, decoration, and interior finishes, electro-mechanical works including low current installation.
C. D. R. WORKS INFRA STRUCTURE BEIRUT 1991-1994 civil works and infrastructure
Activities :
( SUPPLY OF MANPOWER & EQUIPMENT , CIVIL WORKS FOR HIGH VOLTAGE POWER LINE IN FANAR , REHABILITATION OF WATER STATIONS IN BEIRUT),Supply of manpower and equipment for cleaning & removal of debris, rehabilitation of street middle islands, rehabilitation of public waste and storm water networks, (up to 300 labors, 25 pickups, 5 Trucks and one shovel a day).
The civil works for high voltage power line in Fanar include excavation, drawing of power cable, protection, backfilling and asphalting.
The works for water stations include civil and electrical.
MEDITERRANEAN BANK BLDGS INTERIOR CONSTRUCTION ( HEAD OFFICE-VERDUN , MOUSAITBEH BRANCH LANDSCAPING , SUMMER LAND BRANCH) 1991-1994 Modification and rehabilitation of an existing office buildingin Verdun, the Summerlandbranch at jnah,construct a new landscape in Mousaitbeh Branch
Activities :
Renovation of a typical floor building including masonry and concrete works, plastering, accoustical ceiling, tiling and carpeting, wood and metal works, partitions, painting, lighting, electrical power and, bargler alarm system, CCTV, Sanitary works, HVAC ,DATA Network, Sound & Music network , etc...
Works include preparation of shop drawings & as built drawing.
TEMPORARY PRESIDENTIAL RESIDENCE OFFICE BUILDING RAMLET AL BAYDA 1993 One basement and 9 floors old building to be renovated
Activities :
Rehabilitation and modification of existing building including civil & electro-mechanical works, executed within 15 days period, modification of one old residential building to accommodate residence and ultra luxirious offices.
OLD PRESIDENTIAL PALACE OFFICE BUILDING KANTARY 1994 existing old bldg., sand stone bearing walls and facades with pitched roof
Activities :
Rehabilitation of existing old bldg. , sand stone bearing walls and facades . Works to include concrete repair, strengthening, interior finishes & restoration, electro-mechanical works
OGER LIBAN BUILDING OFFICE BUILDING RAMLET AL BAYDA 1994-1995 12 floors and 2 basements office building
Activities :
Rehabilitation and modification of existing offices, including facades.works to include Masonry, electrical power, facades render and treatment, roofing systems, including waterproofing and screed works
ARAB BUILDING RESIDENTIAL BUILDING RAMLET AL BAYDA 1993-1994 basement, G.F entrance, and new facilities including drivers rooms, security doors and systems.
Activities :
Rehabilitation of basement, G.F entrance, and new facilities including drivers rooms, security doors and systems.
BANK BEIRUT FOR COMMERCE OFFICE BUILDING HAMRA 1992 existing offices
Activities :
Rehabilitation and modification of existing offices including civil, decoration, and electro-mechanical works.
ITANI BUILDING OFFICE BUILDING KORAYTEM 1995 9 floors office building
Activities :
Rehabilitation works including civil and Electro-mechanical, and interior finishes
GOVERNMENTAL HERMAIL SERIAL OFFICE BUILDING HERMAIL 1992 Four story building to be designed and executed in lieu of an old existing structure (works to include structural design and shop drawings)Built up Area: 7350M2
Activities :
site investigation, evaluation, Design and shop drawings.